March 19, 2002
Meeting Notes
Approved: 5/7/02
Committee Members Present:
Gail Heit
Ed Houghton
Bill Hyder
Dave Kliger
Steve Kang
Free Moini
Tom Vani (Chair)
Committee Members Not Present:
Suresh Diffenbaugh
Latrice Jones
Introduction:
· Meeting convened by Tom Vani.
· Updates to the 2002-03 Space & Capital binder were provided (Section #7 – Academic Office Analysis).
Discussion of Notes from the
Previous Meetings:
· Notes for the March 5, 2002 meeting were not discussed.
Informational/Discussion/Report Items:
1. Recommended
State-Funded 2003-08 MCIP
Presenter: Fran Owens
Handouts: Start of 2003-08 MCIP with suggested changes
2003-08 MCIP 5-year costs
2003-08 MCIP Summary of Recommendations
· Campus still has no target amount set, but expects a $5M - $10M reduction, meaning our target would be in the range of $150M to $155M.
· Fran’s recommendations were presented and discussed. The University Librarian requested duplicate mention of the point in the Summary of Recommendations that the Library project would be increased by $10.5M.
· Recommendation to put Arts facility ahead of Natural Sciences based on Arts leasing space and needing studio space very badly, as well as the feeling that the campus won’t be able to justify a Natural Sciences Building so soon after the completion of ISB.
· Natural Sciences 6:
Ø ISB really provided space for Environmental Studies, since they could move into Nat Sci II sooner than waiting for ISB.
Ø Suggestion was made to break Nat Sci 6 into three buildings, which would enable the project to be spread over a longer period so that a large amount of funds wouldn’t be needed in any one year. This could be done by department – Physics, Astronomy and Math would each have their own building.
Ø Is Nat Sci 6 so big that there will never be enough money to build it?
Ø Alterations to Thimann may be needed, in association with the new building.
· Added figure for Sinsheimer Building sprinklers.
Ø Walls surrounding corridors do not meet fire code. They must either be fixed or a sprinkler system needs to be added to the building.
Ø Currently exploring cost analysis of both methods. The preference is to add sprinklers.
Ø Building was designed properly, but was not built properly. To try to avoid this from happening again, campus inspectors are involved sooner and more often during construction and the Fire Marshall continues to monitor inspections.
· Alterations to Engineering:
Ø Engineering expected more funds since Engineering II building was designed under the premise that other alterations would be needed to meet certain programmatic needs (such as nanotechnology).
Ø Could nanotechnology labs be added to Nat Sci 6?
Ø Engineering will try to raise private funds to supplement State funding.
Member Items:
2. Gifts
& Purchases of Exterior Public Art
Presenter: Tom Vani
·
How should we decide whether gifted/purchased art
should be displayed?
·
Should principles be established?
·
Should a small group, similar to a space evaluation
team be created?
·
Need mechanism to evaluate quality and appropriateness
of work.
·
Involvement of surrounding building occupants is
necessary.
·
Must also consider costs (maintenance, insurance, etc).
· Handout of topics provided.
Next Scheduled Meeting:
· Tuesday, April 2, from 2:00 – 4:00 at 307 Kerr.
· The 2001-02 schedule will be the 1st and 3rd Tuesdays from 2:00 – 4:00 in 307 Kerr.